Streetscape Update- Week of April 7, 2025

by | Apr 7, 2025

Information provided to the Four Oaks Chamber of Commerce by:

Carter Lovern

Project Manager

Fred Smith Company

Project Progress Overview

Last week-(Week of March 31) We wrapped up underground conduit installation on main street

This week-( Week of April 7) Conduit installation on side streets, hopefully duke energy transferring wires to the new poles if they have a railroad flagger. We will also be grading for curb and gutter.

Next week-(Week of April 14) Pulling wire, grading for C&G potentially pour C&G

2 week look ahead, get C&G started as well as sidewalks.