Information provided to the Four Oaks Chamber of Commerce by:
Carter Lovern
Project Manager
Fred Smith Company
Project Progress Overview
Last week-(Week of March 31) We wrapped up underground conduit installation on main street
This week-( Week of April 7) Conduit installation on side streets, hopefully duke energy transferring wires to the new poles if they have a railroad flagger. We will also be grading for curb and gutter.
Next week-(Week of April 14) Pulling wire, grading for C&G potentially pour C&G
2 week look ahead, get C&G started as well as sidewalks.