Streetscape Update- Week of March 24, 2025

by | Mar 24, 2025

Here is the latest update on the streetscape work provided to the Four Oaks Chamber by: Carter Loverrn

Project Manager

Fred Smith Company

Project Progress Overview

Completed Work (Week of March 17):

  • Continued Electrical conduit Installation

Scheduled Work for This Week (March 24):

  • Continue installation of electrical conduit
  • Finishing working on storm drain
  • Duke Energy Installing new power poles and overhead work

Planned Work for Next Week (March 31):

  • Finishing up electrical conduit work

Long-Term Outlook:

  • Projecting an early April start to retaining walls
  • Dry utility relocation
  • Still looking for a mid to late April hardscape start