Information provided to the Four Oaks Chamber of Commerce by Carter Lovern, Project Manager, Fred Smith Company.
Completed Work (Week of March 1):
- Finished demolition work on N. Main Street and Lassiter
Scheduled Work for This Week (March 9):
- Clean up demolition debris
- Begin installing new electrical conduits
Planned Work for Next Week (March 16):
- Ongoing electrical work through march
Long-Term Outlook:
- Installation of two 65-foot utility poles by Duke Energy.
- Relocate dry utilities to the North side of main street
- Hardscape work tentatively scheduled for mid to late April