Here is the latest update on the streetscape work provided to the Four Oaks Chamber by: Carter Lovern
Project Manager
Fred Smith Company
Project Progress Overview
Completed Work (Week of March 15):
- Continued Electrical conduit Installation
Scheduled Work for This Week (March 22):
- Continue installation of electrical conduit
- Duke Energy Installing new power poles and overhead work
Planned Work for Next Week (March 29):
- Finishing up electrical conduit work
Long-Term Outlook:
- Projecting an early April start to retaining walls
- Still looking for a mid to late April hardscape start