Project Progress Overview

Completed Work (Week of March 15):

  • Continued Electrical conduit Installation

Scheduled Work for This Week (March 22):

  • Continue installation of electrical conduit
  • Duke Energy Installing new power poles and overhead work

Planned Work for Next Week (March 29):

  • Finishing up electrical conduit work

Long-Term Outlook:

  • Projecting an early April start to retaining walls