Here is the latest update on the streetscape work provided to the Four Oaks Chamber by: Blaine Toler
Project Engineer
Fred Smith Company
Project Progress Overview
Completed Work (Week of February 17):
- The electrical team initiated their relocation and setup process.
Scheduled Work for This Week (February 24):
- Demolition of sidewalks on both sides of the road.
- Continued setup by the electrical team.
Planned Work for Next Week (Week of March 3):
- Ongoing electrical work.
Planned Work for the Following Week (Week of March 10):
- Continued electrical operations.
Long-Term Schedule and Milestones:
- Installation of two 65-foot utility poles by Duke Energy.