Four Oaks Downtown Streetscape News Update

by | Feb 7, 2025

 

Here is the latest update on the streetscape work provided to the Four Oaks Chamber by:

Blaine Toler

Project Engineer

Fred Smith Company

Work Completed Last Week (Week of Jan-27) 

Laid storm pipe on Main St near Wellons St

The leg of storm drainpipe will be laid at a later date

Work Scheduled This Week (Week of Feb-3)

Establish sub-grade on Main St

Density testing

Placing stone on Rd for pedestrian access while sidewalks are demo’d

Planned Work for the Following Week (Week of Feb -10) 

Demolition of sidewalks (both sides of the road)

Long-Term Work Schedule and Milestones:

Conduits to be ran for electrical

2 65ft poles installed by Duke Energy