Here is the latest update on the streetscape work provided to the Four Oaks Chamber by:
Blaine Toler
Project Engineer
Fred Smith Company
Work Completed Last Week (Week of Jan-27)
Laid storm pipe on Main St near Wellons St
The leg of storm drainpipe will be laid at a later date
Work Scheduled This Week (Week of Feb-3)
Establish sub-grade on Main St
Density testing
Placing stone on Rd for pedestrian access while sidewalks are demo’d
Planned Work for the Following Week (Week of Feb -10)
Demolition of sidewalks (both sides of the road)
Long-Term Work Schedule and Milestones:
Conduits to be ran for electrical
2 65ft poles installed by Duke Energy