Weekly update provided to the Four Oaks Chamber of Commerce from Carter Lovern, Project Manager with Fred Smith Company.
Last week– (Week of April 7th)-Continued electrical work, fine grading for curb and gutter
This week– ( Week of April 14th)-Continued electric work, testing curb and gutter base, pouring curb and gutter
Next week– (Week of April 21st) Finishing up electric, Dry utility relocation work, Pouring C&G, start grading for sidewalks
2 week look ahead- Sidewalks, Dry utility relocation, Finish C&G, Finish electrical work, Hopefully begin retaining wall work once signal pole issue is resolved.